How we design
Design starts with the risk assessment, not with the roof. BS EN 62305-2 tells us the protection class the building needs, and the class then sets the mesh size, the spacing of the down conductors and the rolling sphere radius the air termination has to satisfy. Working the other way round produces systems that either cost too much or do not comply.
From there it is a geometry problem. We take the roof plan and elevations, apply the protection method appropriate to the shape of the building, and place conductors so the whole structure sits inside the protected volume. On a simple rectangular roof that is quick. On a spire, a mansard, or a building with plant and masts on the roof, it is not.
We use current design software to model this, and we have an accredited BS EN 62305 assessor in house, so the assessment and the design are done by the same people.